Billy Swails Boulevard 4B

BSB 4B

BSB Preferred Alternative and Project Study Area (1-25-2022)

View project synopsis here.

Description

Billy Swails Boulevard 4B is the final roadway segment that would complete what was originally named the Hungryneck Boulevard corridor, a parallel route to US 17 and Rifle Range Road. The anticipated cross-section is a two-lane divided roadway with a landscaped median, turn lanes and bike and pedestrian facilities. The project would join the existing Sweetgrass Basket Parkway on the west to the existing portion of Billy Swails Boulevard to the east.

Status

The project is currently undergoing an environmental review under the NEPA process. An alignment decision has not been made at this time. Engineering work is ongoing.  A PUBLIC HEARING was held on Tuesday, January 25, 2022, between 5:00 p.m. and 7:00 p.m. in the Council Chambers of the Town of Mount Pleasant, located at 100 Ann Edwards Lane, Mount Pleasant, SC, 29464.  Click HERE for more Information.

Public Hearing Resources

Preferred Alignment

Billy Swails Boulevard Segment 4B

Public Hearing Notice

Comment Sheet

Handout

Purpose and Need

U.S. Department of Transportation Act Section 4(f)

Schedule

  • Complete Design:  March 2023
  • Right of Way Acquisition: March 2022
  • Start Construction:  July 2023
  • Complete Construction:  November 2024

BsB 4.7.21

Click here to enlarge

Cost

$14,568,497

Resources

Billy Swails Boulevard Public Information Meeting Handout (5/7/19)

Billy Swails Boulevard Public Information Meeting Comment Card (5/7/19)

Billy Swails Boulevard Public Meeting Notice (4/25/19)

Billy Swails Boulevard Public Meeting Notice (2/27/18)

Billy Swails Boulevard Aerial Display (2/27/18)

Billy Swails Boulevard Public Information Meeting Handout (2/27/18)

Billy Swails Boulevard Network Display (2/27/18)

Approved EA and Draft Section 4f Billy Swails Boulevard Extension 4B  (12/1/21) 

We appreciate your participation and strongly encourage you to provide your input on the project. The NEPA process relies heavily on public input and community participation.  

Comments may be submitted to:

Paul Lykins, Deputy EDS Director, Town of Mount Pleasant at PLykins@tompsc.com

You may also mail your comments to:
Mr. Paul Lykins - Town of Mount Pleasant
100 Ann Edwards Lane, Building A,
Mount Pleasant, SC 29464

A future public hearing will be scheduled for 2022.  


Contact

Paul Lykins, Project Engineer 

  • Ph: (843) 856-3080 
  • Email