Hamlin Trail

HAMLIN BANNERDescription

The Hamlin Trails project is a proposed 10ft concrete multiuse path along Rifle Range Rd from the existing Rifle Range Trails parking area to the US 17 to Rifle Range Rd Connector project multiuse path. This segment will utilize much of the existing Berkeley Electric Coop overhead powerline easement and is intended to include a bridge feature across an existing drainage canal. Staff has submitted a Recreational Trails Program (RTP) grant application for $100,000.00 to assist with construction costs which will be announce in late May of 2022.

Schedule

  • Design Complete:  February 1, 2023
  • Begin Construction:  May 1, 2023
  • Complete Construction:  August 1, 2023

Cost:  

  • $330,214

Resources

Hamlin Trail Project Area Map