Memorial Waterfront Park Phase III

memoiral-waterfront-park_phase-3

Description

This project involves the construction of a First Responders Monument near the existing War Memorial and new features and improved overflow parking in the currently undeveloped area across Harry Hallman Blvd. The First responders monument will feature a large bell suspended by a replica of the bridge towers. This monument will pay tribute to fire fighters, police officers and public service employees that serve our community. New features across Harry Hallman Blvd will include a multipurpose sports court that can accommodate two basketball and four pickleball courts, splashpad fountain play area, pump room, dog park, exercise area, restrooms, expanded maintenance facility, and parking improvements.

first-responder-monument-render

Status

Design Phase

Schedule

  • Notice to Proceed with Design, May 2021
  • Construction Documents, December 2021
  • Submit for permits (SCDOT, Town, SCDHEC, etc),
    December, 2021
  • Advertise for Bids, May 2022
  • Receive Permits, June 2022
  • Receive/Review/Select Bids, July 2022
  • Notice to Proceed for Construction, August 2022
  • Construction Complete, July 2024

Cost

Total: $5,552,239

Future years: TBD

Contact

Steve Gergick, Project Manager

  • Ph: (843) 884-8517 x5556 
  • Email