Description
25,000 square foot facility lined for two full-size basketball courts, four side-to-side basketball courts, four volleyball courts, and four pickleball courts. Will also be used for MPRD wrestling program. Concession area, office space, restrooms, and showers. Exterior access to downstairs restrooms, providing restroom facilities to users of Town Hall field.
Status
Construction phase.
Schedule
Project start date: January 2018
Project finish date - substantial completion: Late December 2018
Project finish date - final completion: May 2019
Cost
Total project: $6,144,000
Resources
Town Hall Gym Schematics
Contact
Steve Gergick, Project Manager