Coleman Boulevard Improvement Project

Coleman Banner_1350x367

For Facts, Two-Week Outlooks, Photo Gallery & More!

Description

The Coleman Boulevard Improvement Projects are an important infrastructure project for the Town of Mount Pleasant. This $18.2 million project is being performed by Blythe Development of Charlotte, North Carolina and is expected to be completed in October 2019. The roadway portion of the total project cost is $14.74M and the utility portion is $3.46M.

This key infrastructure project involves reconstructing Coleman Boulevard between Mill Street and Pherigo Street to create stormwater, roadway and utility upgrades. An adaptive traffic signal system will be installed along Coleman Boulevard to streamline traffic flow and transit amenities such as bus pullouts and shelters will also be installed. Additionally, the project will provide increased travel opportunities for bicycles and pedestrians, decorative street lighting, a way-finding system, landscaped medians and a vibrant activity zone between the roadway and buildings fronting the street.

Coleman Boulevard Construction Update 

March 2019 

Construction is nearly complete on the stage 2 north-bound side of Coleman Boulevard between Simmons Street and Fairmont Avenue and Shem Drive.   Stage 3 median construction is ongoing between Simmons Street and Fairmont Ave/Shem Drive.  Median construction from Simmons Street to Mill Street will start in April after the bridge run.   Currently, the contractor is installing stormwater drainage in Phase 2 (Fairmont Avenue to Pherigo Street), near Brook Green Shopping Center and will continue in this phase with night work while other work items are completed.    Sidewalk and curb and gutter work is nearly complete on Coleman Boulevard from Mill Street to Simmons Street.   All stormwater drainage installation is complete in Phase 1 (Mill Street to Fairmont Avenue and Shem Drive) of the project.  The Mill Street sewer main work is complete.  Mast arm traffic signal poles are scheduled for delivery and installation in April. 

Motorists are advised to use caution and drive carefully through the construction zone. 


Schedule

Start Date:  September 11, 2017

Completion Date:  December 27, 2019

Motorists are advised to use caution and drive carefully through the construction zone.

Project Contact: Ed Barbee, Transportation Construction Liaison – (843) 640-2422