Project Updates

Update 7/9/2018

Trees will be removed in BASIN 4 starting on Wednesday, July 11, 2018. 

Update 7/6/2018

The Snee Farm Drainage Improvement Project is set to begin on Monday, July 9, 2018.

Update 7/2/2018

The construction contract was awarded at the May 2018 Bids and Purchases Committee. Funding from the State Revolving Fund, for up to $10 million, became available July 01, 2018 after the completion of the loan process and the start of the Town’s new fiscal year. The contractor will begin working on July 9, 2018. A formal pre-construction meeting was held with SCDOT, Town staff and the Construction Engineering and Inspection firm. Subsequent meetings with the contractor and utility companies will be held as necessary to prepare for mobilization. Staff plans to conduct several outreach efforts with the neighborhood and directly adjacent property owners in advance of construction to explain the anticipated schedule and phasing plan.